Troubleshooting: ARCN didn’t specify project no., but project no. appears in ledger report?

From AutoCount Resource Center

Question: Why I created an A/R Credit Note without any project, but in Ledger report still show out with project number?

Version: 1.8 / 1.9 / 2.0



Possible Reason:

In A/R and A/P Credit Note, AutoCount will post the entry according to Project and Department defined in the document it knocked off.


Solution:

1. Go to Tools > Options > G/L > G/L Posting.

2. Search for ‘Post by the Project and Department in CN’ and enable it. This means the posting will be in accordance with Project or Department defined in CN instead of document it knocked off.



3. Then, edit and save the A/R and A/P Credit Note. If you have plenty of document need to do so, you can use Repost G/L A/R A/P Transactions function in AutoCount Management Studio.

4. Ledger result will show as below once you done the steps as above mentioned:



By: Julee 170728, CY 170814, P170816


Go to menu

AutoCount Accounting 2.0 & 2.1


AutoCount Accounting 1.8 / 1.9
AutoCount Payroll
AutoCount POS


AutoCount On The Go
AutoCount Accounting Plug-In Documentations