Troubleshooting: System prompt Set Project/Department Posting screen even the gain/loss amount is zero
Question: A/R Receive Payment knock off with Invoice in same exchange rate, but system still prompt set project/department posting screen even the Gain/Loss Amt is 0.00?
Version: 1.9 / 2.0
Invoice, USD 100 (only 1 detail line), currency rate = 4
AR Payment, Payment Amount = 100, currency rate = 4
Possible Reason:
User has enabled ‘Always ask for Project/Department when knock-off’ at Tools > Options > G/L > G/L Posting.
Solution:
Go to Tools > Options > G/L > G/L Posting, uncheck the checkbox of ‘Always ask for Project/Department when knock-off’, and click on OK. Next time, the system will not prompt the set project/department posting screen when you knock-off payment with same currency rates.
By: Ju Lee 230613, Lay Swan 230620, P230626
AutoCount Accounting 1.8 / 1.9
|
AutoCount Payroll
|
AutoCount POS
|
AutoCount On The Go
|
AutoCount Accounting Plug-In Documentations
|